Overview
In early 2024, AuCom contributed to one of Egypt’s largest infrastructure projects: the Elhammam Pumping Stations. Tasked with providing and commissioning cutting-edge motor control solutions under tight deadlines, AuCom’s service team faced the challenge of bringing four 11 kV VFDs (MVH 2.0 Medium Voltage Drives) to full operation within just seven days.
Elhammam Pumping Station, Egypt
The Challenge
The project presented complex demands, including critical replacements and a new update installed. Our team in Egypt required rapid support to ensure seamless integration of the drives with the massive water pumping systems. With strict project deadlines and significant logistical hurdles, successful execution required precise coordination, efficient delivery of parts, and international expertise.
AuCom MVH2.0
Solution: Global Collaboration at Its Best
AuCom’s international collaboration was key to overcoming these challenges. Critical components were delivered to Egypt within days, thanks to our agile global supply chain. The dedicated on-site support from our German team, combined with the unwavering assistance of our worldwide colleagues, ensured every technical requirement was met.
Our MVH 2.0 Medium Voltage Drives, known for their robust performance and energy efficiency, were quickly installed, updated, and tested. The seamless teamwork between our teams across different continents highlighted our commitment to providing personal, ground-level support wherever our customers need it.